At risk · flagged 2 weeks running

CRM migration

Owner: Tom Okafor · Go-live: 30 November · Budget: 94% used

Open in this week's report

Jira shows the project on track, but data mapping has used 128% of its budgeted hours and the integration has had no changes for 11 days. The 30 November go-live is unlikely without a decision this week.

Why it was flagged · 4 sources

Harvest · Data mapping at 128% of budgeted hours186 of 145 hours
TaskBudgetUsedOver
Legacy contact records4071+31
Alumni giving history3548+13
Event attendance3034+4
Consent records4033−7

Time entries 1–18 October, 9 people. Synced today at 06:30.

GitHub · No integration changes merged for 11 daysLast merge 8 Oct
  • PR #214 · Contact sync: map consent fields · opened 8 Oct · awaiting review
  • PR #217 · Alumni giving import job · opened 8 Oct · awaiting review
  • PR #219 · Retry failed sync batches · opened 8 Oct · awaiting review

3 open pull requests awaiting review on the integration repository. Synced today at 06:30.

SharePoint · Supplier data addendum still unsignedDue 22 Oct

Found in /CRM/Contracts/Data-Processing-Addendum-v3.docx · last edited 2 Oct. No signature block completed.

Jira · 78% of tasks done; team status "On track"96 of 123 tasks
AreaDoneOpen
Data model and design310
Data mapping426
Integration1513
Testing and training88

The 27 open tasks include all integration and testing work. Notes on CRM-212 mention duplicate records from a 2019 import.

Status history

  1. Wk 38On track
  2. Wk 39On track
  3. Wk 40On track
  4. Wk 41On track
  5. Wk 42At risk
  6. Wk 43At risk

Recommendation

Escalate the supplier addendum today. At Wednesday's steering group, agree three weeks of extra data-mapping resource (about 60 hours) to hold 30 November, or plan a move to 14 December.

Checked by Sarah Bertorelli · 07:40 today